ADIF, Spain
COMMERCIAL APPLICATIONS
HIGH SPEED NETWORK
Madrid Zaragoza
- Lérida
- Tarragona
- 460 Km
- In operation with ERTMS Level 1 at 300 Km/h
- ERTMS levels 1 & 2 installed
- Level 2 is being tested at present. In commercial operation at 350 Km/h by the end 2008
- Supplier: ERTMS trackside: Ansaldo
- CSEE Transport
Lérida – Tarragona
- 90 Km max
- speed 350 Km/h
- ERTMS Levels 1 & 2
- In operation with ERTMS Level 1 at 300 Km/h
- Level 2 is being tested at present. In commercial operation at 350 Km/h by the end 2008
- Supplier: the consortium Thales, Dimetronic (Invensys), Indra and Siemens
- In operation with ERTMS Level 1 at 300 Km/h
Taragona
- Barcelona
- 100 Km
- max. speed 350 Km/h.
- ERTMS Levels 1 & 2
- Supplier: the consortium Thales, Dimetronic (Invensys), Indra and Siemens
- Under construction. Entry into operation by the end of 2007.
Madrid – Valladolid
- 200 Km
- max. speed 350 Km/h
- ERTMS Levels 1 & 2
- Segment Segovia
- Valladolid (82 Km) assigned to the consortium Thales, Indra, Invensys, Siemens
- The rest of the line is assigned to the consortion Thales, Invensys and Siemens
- In operation with ERTMS Level 1 at 300 Km/h
Cordoba-Malaga
- 155 Km.
- max. speed 350 Km.
- ERTMS Levels 1 & 2
- Assigned to the consortium Thales, Invensys, Siemens
- In operation with ERTMS Level 1 at 300 Km/h
Toledo Access (La Sagra – Toledo)
- 25 Km
- max. speed 220 Km/h.
- ERTMS Levels 1 & 2.
- Assigned to the consortium Thales, Indra, Invensys, Siemens
Zaragoza – Huesca
- 79,5 Km
- In operation with ASFA
- max. speed 200 Km/h
- ERTMS Level 1
- ERTMS trackside assigned to Alstom
More information can be found on Adif
Conventional Network
- Albacete – La Encina
- Section of 93 Km
- Speed 220km/h;
- ERTMS Level 1
- Supplier: Trackside: Bombardier
MADRID COMMUTERS LINES
- Several sections up to 160 Km
- This represents approximately half of the Madrid Commuters Lines
- Speed 220km/h; ERTMS Level 1 & 2 (in some sections)
- Supplier: Trackside: Consortium Alcatel and Dimetronic (Invensys)